Haslemere- School Improvement works

Following flooding to the artificial pitches we were instructed to install new surface water drainage and alter the layout of the road and pathway. Catchpits and detention areas were constructed and new edgings and kerbs were installed. Areas were built up with MOT type 1 ready to recieive tarmac. Turf was also then laid and finally tarmac surfacing was completed. The pitches can now be enjoyed without puddles!