Working at height and hot works made this project challenging as well as moving around the site to access the 800m long attraction. The track and columns from the monorail were slung ready for the lift, then operatives would use MEWP's to access each area where they would gas cut each section of track and column. Each section was lifted onto a trailer and removed off site. The bases were broken beneath ground level and tarmac was laid to reinstate areas.