Another concrete hardstanding with drainage completed. Using our 8 tonne excavator we reduced the levels to 0.5m then laid a new 0.3m thick sub base with a reinforced concrete slab 0.2m thick. Heavy duty drainage channels were installed meaning this area will soon (after sufficient curing time) be ready for HGV's and forklifts. For the concrete pour we used a 30m boom pump to make life as easy as possible.
Although it was dry, we battled the cold weather on this project to ensure suitable temperatures on the days we poured the concrete. What a great result!